Residents in parts of Johannesburg will get a three-day break from load shedding after Eskom granted the waiver request submitted by the City earlier this week.
The urgent request arose from an accumulation of power outages in several areas affected by flooding due to torrential rains.
The affected areas were the greater Roodepoort area, Hursthill, Northcliff and Lenasia.
On Monday, City Power said it had received 4,000 outage calls from affected areas. More than 2,000 calls came from Roodepoort.
“City Power is still under pressure to deal with multiple unrelated outages following severe thunderstorms and flooding. The situation is exacerbated by the higher stages of load shedding,” it said.
ROLL-UP COVER | Eskom and cargo shedding news as it happens
He attributed other power outages to cable theft, cable failure and vandalism.
Eskom said: “Through the collaboration between the two entities and in accordance with the regulations of the South African National Energy Regulator, Eskom was able to assist during this period.”
We live in a world where fact and fiction blur.
In uncertain times, you need journalism you can trust. For 14 free days, you can have access to a world of in-depth analysis, investigative journalism, featured opinions, and a variety of features. Journalism strengthens democracy. Invest in the future today. Thereafter, you will be billed R75 per month. You can cancel at any time and if you cancel within 14 days, you will not be billed.